Once the ball got rolling it all went pretty fast and relatively smoothly, at least from the outside perspective and thanks to supportive friends. The house had to come down for the City to sign off on the partition. A week before my deadline the house came down, the surveyor finished the final plat, after some back and forth with the County Surveyor he signed the final plat, the city signed the plat and today (11 June 2012) the plat was recorded with the county. Another lot added to the tax rolls for Hood River all within the deadline - whew! Next week the foundation goes in.......
Salvage windows - unfortunately there wasn't much else to salvage |
Fire Department training night - they were excited to have a house to tear up with chain saws. |
First thing Monday morning the equipment showed up and the excavators went to work - lucky for me it was a rainy day to keep the dust down. |
Day 1: house down and getting hauled away to be burned and to the landfill. |
Day 2: house hauled away and the prep for the foundation done. |